Pages

Wednesday, 3 August 2011

HBA cabling progress — 03-Aug-2011

Array cabling complete! Today we put in the last cable connecting the antenna tiles to the RF-container patch panel. This was accomplished around the middle of the day; somewhat ahead of the revised schedule, which was good. For completeness, here is the final cable progress map:This ends another important phase of the project. Ooo... but that there is a lot more to go yet!

Firstly, the cable mausoleum needs to be completed, as well as the remaining RF-container preparation work. For the next few weeks we will be doing a lot of site work too. Snow fences, wind breaks, and lots more. Of course we will be posting about all of these on this web log.

And, hopefully, we'll get the first science measurements soon!

No comments:

Post a Comment

Note: only a member of this blog may post a comment.