Optical fibre connection

Following on from the recent post about the wireless radio-link connection, there is also the installation of the actual optical fibre. This is connected around the northwest and north edges of the site and is buried into the ground. The following photograph taken last year before any snow fell, shows the digger putting the final stretch of trench in place (very carefully!).


The optical fibre has now been buried into the ground and is secure. The end terminates inside the RF-container and connects us to the outside world.

Monday, 26 March 2012

Network connection

More news from the end of last season! An "out-of-band" network connection was made between the RF-container and the outside world. This provides a low-capacity data stream for administration and service use. It can also be used for low-data-rate tests and other small-scale experiments which are controlled remotely.

Left: The data-link mast is installed. Right: first connection test

The capacity of this link is typically only 3 to 4 Mbits/second, which is only 1/1000th of the date output capacity of the site overall. For that, a 4 Gbit/second link would be required, but when installed, that will give KAIRA full data capacity for linking into to EISCAT_3D or even the main LOFAR network.

Sunday, 10 July 2011

Internet connection

Although a super-high capacity dedicated data link is planned for the site, this is a long-term project and some level of basic connectivity is needed in the short term. For this, we are using a point-to-point radio Internet link.

The antenna for the link is actually quite small (although remote, the distance that we need to travel is not too great), but the antenna needs to be mounted quite high to ensure that we get good clearance over ground cover to establish the point-to-point link.

Fitting the antenna to a mast on the Lehtinen Barracks.

We hope to have this system operational in the next day or so. This will allow remote monitoring of the site and act as our out-of-band link for equipment control and configuration.