On 12th July 2012, we installed our first low-band aerial. Although we have installed several around the sites before (three at Kilpisjärvi and two at Sodankylä), this one is different. The reason for this is that it is the first LBA to be installed in the "final" location on the field. In other words, we have started installation for real!
As you may remember from last year, we reported on the installation work of the HBA tiles. Well, as we have a lot of curious colleagues, we intend to do the same with the LBA as well. As a result, we will be putting up progress maps as we go along, showing the newly installed aerials. Although a bit empty at the moment, here is the first of them!
As we go along, we'll be interspersing these progress maps with photographs of the build. Enjoy!
Showing posts with label construction. Show all posts
Showing posts with label construction. Show all posts
Saturday, 14 July 2012
LBA installation progress — 12-Jul-2012
Friday, 6 May 2011
Construction plans — Part 5
With the cabling run out, the next stage is to install the internal electronics within the RF-container. Within it there are four, full-height 482.6mm (19") rack frames. The sub-rack assemblies go into the first three of these and the fourth is for the control computers, clocks and networking. Once the sub-rack assemblies are in place, they can be cabled up with the white signal cables that come from the back of the patch panels.In addition to this, site clean-up and storage will be done. This means 'dressing' the site, securing all items, packing up equipment and recycling waste. The site is then cleared and we are ready for winter.
Over winter 2011-2012, the first tests between KAIRA and the VHF transmitter at Tromsø will be carried out. And then, in the following year, the LBA will be deployed and the data connection made back to the supercomputer in Groningen.
But that's another story.
So ends our mini-series on what is planned for the summer installation... and the action starts NEXT WEEK!
Labels:
construction,
LOFAR,
planning,
RF-container,
Tromsø,
VHF
Thursday, 5 May 2011
Construction plans — Part 4
There are two massive tasks planned for July. This is the month with the best weather, 24-hour-a-day sunshine and the warmest temperatures (sometimes even exceeding 10 celsius). During this month the HBA tiles will be deployed and then they will be cabled up. This is also the month when the largest part of the workforce will be on the site.The HBAs are deployed in a semi-sparse pattern. Although we have a final design in mind, this will not be confirmed for certain until the end-of-winter test evaluation has been completed. In any case, the pattern will be in small groups of antennas, oriented towards the VHF Tromsø transmitter, and set so that they are compatible with an upgrade to a full international LOFAR station HBA field.
Although there are only 48 HBA antennas, the plan is one day to expand this to the full 96 tiles (+1 dummy tile). The KAIRA project still has a full LBA (96 aerials) and RF-container, but there is a smaller HBA installation in the first instance.
Additionally, the HBA will be built on a raised platform. This is for a number of reasons. Firstly, it assists in snow control. Drift snow can be a problem, so by raising the antenna field, it allows the wind to blow snow and thus help clear the array naturally. Additionally, it decouples the tiles from the ground, thus giving us a lot more flexibility with the drilling of anchors for the framesets. Finally, it lets the cabling be done above the ground which, apart from protecting the cables from the frost, makes installation and repair access so much easier.
The frames are 1.5 metres high. As the tiles themselves are 0.5 metres high, this puts the top surface of the HBA approximately 2 metres above the ground.
In order to deploy the HBA, the framesets need to be assembled from their component frames. They are then lifted into place, as per the precision surveyed marker pegs from the array layout survey. They are anchoured to the ground and each other to form the secure platform for the HBA tiles.
Once each frameset is in place, the HBA tiles themselves can be deployed. The tiles are delivered by lorry to the storage area on the site. They are then moved by all-terrain forklift to the unfolding area, where the packaging material and securing harnesses are removed, the tile is unfolded and fitted. The tile is then lifted by crane onto the frameset, where it is anchored into place and the cover is applied.
This procedure is repeated until the total deployment is completed.
Once the HBA tiles are in place, the cables can start to be connected. There are a pair of cables for each tile. They run back to the RF-container where they are connected to a patch panel. Each cable is a coaxial-type and will carry the RF signal in one direction and power and commands in the other direction.
Because it is important to control the cable lengths for the LOFAR radio telescope, each cable is made to a specific length. And to ease the manufacturing process, these lengths are standardised to a small number of set lengths. Because of the positions of the HBA tiles, there can be several tens of metres of excess cable which needs to be carefully zigzagged back and forth before the remainder of the cable goes into the RF-container.
Typically, this is done underground; cables on all LOFAR stations are buried. However, for KAIRA, the cables must be kept above the surface due to the agressive ground freezing. Thus rather than excess cable length being stored in a 'cable grave', it is instead stored in a raised box — the so-called 'cable mausoleum'.
Wednesday, 4 May 2011
Construction plans — Part 3
Starting on the 6th June 2011, the main site works begins. In the first instance, this means setting up the site and establishing an operations base. Mundane items such as storage cabins, site power and water need to be set up. Then site mark out can occur. Some of this is low-precision marking (indicating parking, transit and storage areas), but there are some precision surveying items that are done at this time. This includes the set-out of the reference marks, which will be used for the main array surveys.For site power, feeder pillars need to be built, which means trenching, concrete foundations and termination points. Cable will need to be drawn/laid and then tested before final power is applied. Fortunately for us, there is a power source point not too far away from the site, so the additional stretch that will need to be covered is only a few hundred metres.
In the meantime, the ground works will have started. This means the rough levelling of the site, application of the drainage pipes (there will be agricultural drains put under the base soil, to facilitate drainage of water and thus minimise the impact of ground freezing in the autumn.
Once the pipes are in place, the cover soil is put in place, and then smoothed to get it roughly level. This is then washed and left to stand for 24 hours, before being checked for level, and packed solid again. This ensures that we have a firm based on which to deploy the HBA.
While this has been going on, work on the RF-container will have started. The RF-container is the standard shipping crate which will contain the signal processing electronics. In order to put this onto the field, a suitable area must be established for it. So an area of ground will need to be prepared, following a placement survey. The foundation holes will be drilled and a steel support frame put in place. The container is actually mounted on this frame, above the ground. The reason for this is that it allows snow to pass underneath, provides an easier way to level the container on the rough ground, the raised placement serves as additional container-to-ground isolation and it will make the cabling from the arrays easier.
Once the frame is in place and leveled, then the holes can be backfilled and concreted thus completing the preparation of the container location. The RF-container can then be delivered to the site and deployed, ready for fitting, installation and commissioning.
At the end of June, there is a small pause for the mid-summer, and then the work resumes in July.
Tuesday, 3 May 2011
Construction plans — Part 2
The first major site work will take place in about the second week of May 2011. This is the first large-scale site visit since the deployment of the test tiles last autumn. Although there have been numerous inspections over winter, they have been passive only and this work in May will be the first time that we interact with the site.The first task of this site work will be to clear the snow. At present (02-May-2011) there is still 30 to 40 centimetres of snow over the HBA area. In order to get sufficient ground thaw, this snow has to be moved so that sunlight can strike the dark ground directly and thus cause surface warming. Once that happens, then not only will it permit the ground frost to thaw, but it will also limit the impact of fresh snowfalls which, although uncommon, are still possible in the sub-zero temperatures. We should note that we are getting close to the midnight sun season, so that means 24 hours of sunshine per day (clouds permitting).
The second part of the May site works will be the evaluation of the test tiles. These two tiles were deployed last year under snowy conditions. In order to limit the amount of drift snow that banks up on or against the antennas, the KAIRA project plans to put the high-frequency tiles on a raised platform, made from a series of frames. By raising the tiles, they will be subjected to greater wind speeds and will avoid the immediate ground boundary layer.
To test this, and various other concepts, two test tiles were placed on the site. They have been monitored over the winter and now is the time to give them a full inspection to examine them for water incursion, ice packing, cold damage, ice shift damage, cracking and deformation and lateral displacement.
Once that has been done, there will be a destructive test performed on the tile. Although the tiles are well understood from a theoretical point of view, it remains to be seen how they fare when faced with real punishment. Thus, a sequence of destructive tests will be carried out to evaluate their ability to withstand shocks, pressures and various other types of duress that could be applied by severe snowfall, ice build-up or other forms of physical damage.
At the conclusion of these tests, the site will be cleared and left to thaw out in the spring sunshine.
Throughout the entire process, there will an extensive set of photographs taken, and numerous reports made here on the KAIRA web log.
Monday, 2 May 2011
Construction plans — Part 1
"So, all of time and space, the entire history of the universe, every star, every planet... where do you want to start?"This is it, May 2011 and the ice is about to melt. In less than three months we will have completed the High-Band Array (HBA) of KAIRA. Lots of questions, lots of challenges, lots of plans and... lots to do!
Let's take a moment to recap where we are, what we are doing and map out what we can expect over the course of what will be a very challenging summer.
As we write this, we are in the midst of the planning phase. This means working out the details of the schedules. Although a general strategy was worked out some time ago, the intricate details of the deployment need to be worked out and equipment lists and staff rosters drawn up. It also means the placing and evaluating tenders for any local contractor work.
There is also a large amount of documentation that needs to be completed, ranging from supplementary material for the planning applications, through to the site and traffic management plans, risk assessments, tool inventories, first aid and emergency procedures, safety equipment preparation, and organising accommodation.
The next few articles are going to explain what is going to happen over the course of the next three months.