Showing posts with label frames. Show all posts
Showing posts with label frames. Show all posts

Sunday, 24 June 2012

Sorting out the woodwork

In order for the LBA to be placed, the left over woodwork from the HBA frameset build needed to be moved.


This was done by the RAL/SGO team by hand.


In no time we had everything cleared up and sorted out ready for the LBA ground works. In the second photograph, the LBA grids are on the left, spare frames in the centre and left-over HBA pallets on the right. All the left-over timber will be re-used to build snow fences to help protect the aerials and tiles.

Sunday, 14 August 2011

Trimming

With the cabling finished, there were just a few minor adjustments to be made to the woodwork.


Here, Pertti Nissinen trims a beam to allow the final cable dressing to be done neatly.

Tuesday, 19 July 2011

Final frameset

Well, the final frameset has been assembled and moved onto the HBA field. That's 48 framesets, or 336 individual frames. It is also 192 batons and 192 diagonal braces too. And so very many nails.

A lot of people have been involved in the work on the framesets, from the original design and prototyping through to the bulk assembly and setting them out on the field. We are grateful to all of them, as the project relies so much on getting this part of the system correct.

However there are two who need a special mention. They are:

Rauno Oikarainen

Pertti Nissinen

These two have done the bulk of the frame assembly work and have kept just ahead of the tile deployment, meaning that we've never had a hold up on deploying tiles.

On Monday 18th July 2011, the final frameset was assembled and put onto the field (although we still had a couple left in storage... these would go on later). Fittingly, they both signed it with their names and the date.

With that done, the construction template could be dismantled and the area cleared away for the next major KAIRA timber project... which will start very soon!

The last frameset to be put onto the field went to location H31 on Tuesday 19th July 2011. It was one that we had built earlier, but this was the last one to actually go in.

So, to Rauno and Pertti, and everyone else who helped with the work on the framesets...

Thank you! / Kiitos!

Thursday, 7 July 2011

Completing the frameset installation

Once the framesets have been put in place, they need to be secured. Additionally, we have decided to provide some additional batons on the frameset to ensure stability and to help support the HBA tile that will be placed on top of it.

Fitting extra batons to support the HBA tile.


Attaching frameset to the anchor lines.

The attachment is made with an O-ring and S-hook, shown in the next image. They connect from a screw in the frameset (top right) to the black nylon loop from the anchor (lower centre-right).

The parts that attach the frameset to the anchor lines.


Once these additional actions have been taken, the HBA tile can be placed on the frameset. The frameset system is essential for our site, in order to cope with the snow drifts. It also sets us apart from other LOFAR stations... while most LOFAR stations look the same, there'll be no mistaking KAIRA!

(Coming next... photographs of the first tile deployment!)

Photos: D. McKay-Bukowski

Saturday, 2 July 2011

First frameset

The first 'real' frameset for the installation has been assembled (although it has not yet been lifted into place). The main objective here was not quite to get the frameset itself built, but to practice the technique and ensure that the auxiliary equipment, templates and rigs were working.


Each frameset comprises seven frames. Five of these are 4900mm long and align in one direction at a spacing of 1250mm. The other two frames in the set are 5000mm long and go in a cross-wise direction to the others.

See also: http://kaira.sgo.fi/2011/06/frames.html

Friday, 10 June 2011

Moving frames of reference

When the frames were delivered to the site, it was not possible to put them in the optimal storage location, due to the rugged terrain on the field. Well, now that the first stage of the levelling has been completed, it has been possible at last to move them into the ideal location ready for their use in the main build.

Thus, on 8th June, we moved all 350 frames and the stored test tile across the site to a newly prepared area.

The 15-tonne digger prepares to lift one of the frame stacks.


It is then driven across the HBA field to the other side.


And finally set down in the new stack position.

Photos: D. McKay-Bukowski

Thursday, 9 June 2011

Frames

As mentioned in the earlier post, a total of 350 frames have been delivered to the KAIRA site. Every HBA tile will be mounted on a total of 7 frames. There are 5 that go across the tile, supporting the inner cell walls. Then there are 2 at the end. The end-frames (Type-R1) are slightly different to the cross-frames (Type-R2), but only in length (5000mm and 4920mm respectively). The basic shape is the same, as is the thickness and height.
The quality of the workmanship is stunning. All the timber is fully dressed and the accuracy of the dimensions is exceptional. This first image, shows the mark-up on one of the stacks... isn't the grain of the timber lovely!

Here's a picture of the author (thanks to Markku Postila for taking the photograph!). This photograph should give a reasonable idea of how big these frames are, and how high the antenna tiles will be when they are finally placed on top.
All the beams are dressed pine. The lowest beam, however, has also been pressure treated (no, not by me sitting on it!), as it needs to be in direct contact with the ground. There are no nails or screws per se, but the joins are held together with spiked plates that hold the timber in position.

When stacked together (in bundles of 30 frames), they form these tunnels, which have that amazing smell of freshly worked timber.

Friday, 27 May 2011

Destroying LOFAR — Removing the frame

The final stage in clearing the area where the raised test tile was, is to get the frame itself out of the way. This also provided a useful test in that we could experiment with the moving of an entire frame using the 15-tonne digger provided by the local Kilpisjärvi contractor.

Markku Postila and Toivo Iinatti attach the lifting straps.


The frame is moved off the edge of the site.

With the frame completely moved, and ground tile also gone, the site is now fully clear ready for the ground preparation work for the complete build.

Ground works will actually start in a few weeks, giving plenty of time for some surface thawing of the ground, making it easier to work with.

Thursday, 26 May 2011

Frame anchor condition

As we saw in our article on the ground tile anchors, they held firmly in the ground and the snow drifts did not affect the translation or tension on them. As it turned out, the anchors holding the raised tile to its frame, and the anchors that in turn hold the frame to the ground fared even better. Here are a few photographs (taken before the tile collapse!) of the anchors holding the frame to the ground lines.




One thing to note is that the anchor lines remain vertical. What this means is that the frame has not shifted in any way. One of our concerns was that wind and snow loading would cause the antenna tile or the support frame to shift (similar to our shift-checks on the ground tile). As it turns out there is no evidence of even the slightest displacement.

Monday, 16 May 2011

Frames delivered

It's getting serious now. Shortly after the winter testing was completed and cleared away (although we've still lots to report on this), we had the delivery of all the frames for the High-Band Array (HBA).

In total there are 350 frames (we need 336 for the antennas, plus another 10 or for cable looms, and then some spares).

These are in the middle of the array area at the moment, so they will need to be moved later, but delivery can't be done quite the way we wanted it due to the fact that the ground is extremely rocky in places still, and it is not possible to get the delivery lorry into the exact place we want it.

Tuesday, 19 October 2010

Deploying the test tiles

Today the two test tiles were placed on the site. A snow-plough lorry with a loader crane was used to lift the tiles into position. For the tile that was put directly onto the ground, this was moderately straightforward. However, the raised frames made things somewhat more tricky.


Once the tiles were in place, the lids and covers could be applied. We'll no doubt explain this in more detail when we write about the actual placement of the final antennas. But for now, it will suffice to say that this means applying covers and securing the tiles to the ground.

As it turned out, we were just in time. As the second tile was placed and we started the covering and securing, the snow started to fall. Within 10 minutes, there was already a reasonable dusting of snow over the tiles, tools and equipment.

In the foreground of this image, the low tile can be seen while in the background the raised tile is still being secured.


With the work done, it was time to clear up. Safety markers were put up around the area and signs were erected to explain what on earth these strange things are!


The signs explain that these are antennas under test. They are written in four languages: Sami, Bokmål, Finnish and English.

Sunday, 17 October 2010

Frames to go!

In order to limit the amount of drift snow that banks up on or against the antennas, the KAIRA project plans to put the high-frequency tiles on a raised platform, made from a series of frames. By raising the tiles, they will be subjected to greater wind speeds and will avoid the immediate ground boundary layer.

To test this, and various other concepts, two test tiles will be deployed at the site this year. They will be monitored over the winter and fully inspected in the spring. Of the two tiles, one will be placed on a 1-metre high platform and the other directly to the ground (like is done at conventional LOFAR sites).

The deployment of these test tiles will be carried out over the next couple of days. And, although the tiles themselves will be delivered directly to the site, the frames will be taken up from the institute.

In this photograph, the set of timber frames has just been loaded onto the trailer, ready to be towed up to the site.