Today we only completed a single LBA aerial. However, we started a lot! Given the current conditions, the requirement to make more 40-metre cables and the added complication of having to scan the new half-lengths, the crew decided to try to get as much 80-metre cable work done as possible, giving the others a chance to make some headway on cable production. So, in total we installed 13 pairs of 80-metre cables, and quite a few pairs of 40-metre cables, but the aerials themselves have not been installed... except just the one!
Obviously we shall resume work tomorrow and, hopefully, have a more impressive progress map to show at the end of the day. But, for now, the good news is that we are now past the half-way mark.
Overnight, the observing team will continue to work on calibration and collecting test data.
No comments:
Post a Comment
Note: only a member of this blog may post a comment.