Monday, 4 July 2011

HBA installation progress — 04-Jul-2011

Although nothing has been deployed onto the field just yet, we're including this update map as a record of the situation.In particular, we can report that the first frameset has been assembled off-field, ready to be transported onto the array tomorrow. Additionally, there are now 8 HBA tiles delivered to the site. We should at least start to see the map fill in tomorrow, with the first frame planned for installation on 5th July.

No comments:

Post a Comment

Note: only a member of this blog may post a comment.