The day started with the early delivery from two lorries. That meant eight new tiles. And, as it turned out, that was precisely what we installed today. We are back on schedule.
Despite needing a short break due to a heavy rain shower that came through, and some slight delays when we needed to correct the ground levels on locations H39 and H28, we managed to get eight tiles installed. We did have a number of framesets ready, so that certainly helped, as did the fact that these did not have quite so far to travel.

Additionally, we managed to get the last frameset completed today. This means that the last frames are produced and are ready to be lifted onto the field first thing in the morning. As a result, we concluded the day by dismantling the construction template for the framesets.
Tuesday will see the last of the tiles deployed. Although there are only three there, it is going to be a challenging day, due to some unexpected problems. More on that tomorrow!